Timeline & Process

Return to MWELO

MODEL WATER EFFICIENCY LANDSCAPE ORDINANCE (MWELO)

Step 1

Sections A through D must be submitted prior to permit issuance:

  1. Project Information Sheet

  2. Landscape Site Plan

  3. Plant List

  4. Plant Materials and Irrigation Requirements

Step 2

Sections E-F must be submitted prior to final building inspection:

  1. Sub-meter for projects over 1,000 square feet

  2. Certificates of completion and installation, irrigation and maintenance schedule